Construction of road and pavement by asphalt

Project location :Salah Aden province

Client :Bridges Salah Alden, Salah Alden Governorate

Contract Value (US$) :(US$):

Contract Duration: 9 Months

Contract Start Date:2008-05-20

Contract Completion2008-10-20

Scope of work:

The contract contains the following activities.

  1. Cutting/Trimming and Excavation of the Damaged Roads.
  2. Filling works, filling the excavated places beneath the asphalt pavement with sub base.
  3. Asphalt concrete layer (Stabilizer Layer)
  4. Asphalt concrete layer (Binder Layer)
  5. Reinforce concrete ford (Crossing) (water pass)
  6. Concrete works for Walkway, Casting (10cm thick) plain concrete using sulphate resistance cement and (C25MPa) concrete
  7. Traffic lines, marking applied, with approved motorized equipment's or truck- mounted units, including surface preparation
  8. All works accordance with Iraqi standard for road and bridges.

Photos

Projects
Send us a message

Our Contacts

Address

AI-Zwyia-Baiji, Salahuddin - Iraq 126 English Village, Erbil - Iraq

Al-Mutanaby
neighborhood - Baghdad - Iraq

Al-Baradya zone - Basra - Iraq


Email

info@alkhatabco.com 

alkhatab.almutahida@gmail.com


Mobile

009647708506005

009647517106759

009647834140505