Rehabilitation of Al-Sikak bridge in Baiji

Project location :Salahudeen Governorate.

Client :UNDP

Contract Value (US$) :(US$):

Contract Duration: 360 Days

Contract Start Date:2023-10-21

Contract Completion2023-10-21

Scope of work:-

AL KHATAB AL MUTAHIDA Co. had been contracted with(UNDP to Rehabilitation of Al-Sikak bridge in Baiji / Salahudeen Governorate.)

  1. Site Preparation:
  2. Warning Signs,Permanent Signs,Temporary Signs.
  3. Concrete Works,Blinding Concrete,Reinforced Concrete,Abutment,Piers with concrete bases pad (50*50*5 cm),Foundations,diaphragm beam,approach slab,Deck slab.
  4. Bearing Pads and Precast Concrete Girders,Elastomeric Bearing Pads,Precast (pre-tension) Concrete Girders.
  5. Precast (pre-tension) Concrete Girders:install reinforced concrete girders (Pre cast pre stressed T section) type as details below:The compressive strength for the concrete not less than 55 MPa.
  6. Backfilling Layers.
  7. Pavement, Sidewalks & Expansion Joint,Approaches pavement,Bridge Pavement.
  8. Expansion Joints.(install waterproof expansion joint seals (chloroprene) type T100)
  9. Thermoplastic Paint for Road Marking.
  10. Bridge Walkway Painting.
  11. Sanitary Works.
  12. Galvanized Steel Guardrail on The Bridge walkways.
  13. Solar street LED.

Photos

Projects
Send us a message

Our Contacts

Address

AI-Zwyia-Baiji, Salahuddin - Iraq 126 English Village, Erbil - Iraq

Al-Mutanaby
neighborhood - Baghdad - Iraq

Al-Baradya zone - Basra - Iraq


Email

info@alkhatabco.com 

alkhatab.almutahida@gmail.com


Mobile

009647708506005

009647517106759

009647834140505