Supplying and erecting scaffolding cablc type conform to EN39, EN10219, and ASTM standards.
Project location :Sulaymaniyah PLG Khor more satiation
Client :Biltek Uluslararasi Insaat Limited Sirketi.
Contract Value (US$) :(US$):
Contract Duration: 600 Days
Contract Start Date:2022-03-07
Contract Completion2023-11-07
SCOPE OF WORK:
Supplying and erecting scaffolding cablc type conform to EN39, EN10219, and ASTM standards.
NO |
Item Description |
Unit |
Quantity |
Length cm |
1 |
Scaffolding Horizantol Pipe |
Piece |
2,000 |
80 |
2 |
Scaffolding Horizantol Pipe |
Piece |
3,000 |
100 |
3 |
Scaffolding Horizantol Pipe |
Piece |
5,000 |
115 |
4 |
Scaffolding Vertical Pipe |
Piece |
1,000 |
150 |
5 |
Scaffolding Vertical Pipe |
Piece |
2,000 |
200 |
6 |
Scaffolding Vertical Pipe |
Piece |
3,100 |
300 |
7 |
Bottom Brackets |
Piece |
3,100 |
200 |
8 |
Top Brackets |
Piece |
3,100 |
330 |
9 |
Timber I beam |
Piece |
1,000 |
390 |
10 |
Timber I beam |
Piece |
1,000 |
450 |
11 |
Timber I beam |
Piece |
1,200 |
450 |
12 |
Timber I beam |
Piece |
1,200 |
490 |